Scope of Work
- Grading and site preparation
- Supply of materials and installation of all foundations on site
- Supply of materials and equipment required to complete the switchgear and control building
- Design, supply and assembly of steel structures
- Supply of a package of electrical equipment and installation of all electrical equipment including that free‐issued by the owner
- Supply and installation of all power and protection cabling required for the project
- Testing and commissioning as a joint effort between the Owner, HONI and EPTCON