EPTCON Ltd. provided EPC Services for this 230 kV Interconnect Switchyard for a 100MW wind farm

Scope of Work

  • Electrical and Civil Engineering of the Switchyard & Engineering of the Protection and Control System
  • Grading and Site Preparation
  • Supply and Connection of the Control Building including the Supply and Installation of the Distribution, Protection and Control Equipment housed within it
  • Supply 34.5kV Switchgear and Prefabricated Building
  • Supply and Assembly of Steel Structures
  • Supply of package of Electrical Equipment and Installation of all Electrical Equipment including the Owner-Issued 230 kV Circuit Breakers